Merseyrail - Sandhills Kitchen and Welfare Refurbishment


PROJECT

Sandhills Kitchen and Welfare Refurbishment


CLIENT

Merseyrail


SECTOR

Rail


THE BRIEF

Design and Installation of the Kitchen and Welfare Unit at Sandhills Station

THE SOLUTION

The scheme was managed and delivered by SIS Projects.  The works were carried out over a 4 week period and completed on time.

Summary of works:

Design Pack, Temporary Facilities, R&D Asbestos Survey

Strip out all existing services.

Replacement of Kitchen units and High end appliances.

Flooring, Ceiling, Window Manifestations,

M&E including new electrical supply and local distribution board, including fire dampers.

Powder coat paint existing steel window frames to new colour.

Full Furniture package fit out.

 

 

Posted in Projects.